Monterey Reserve Master Plan Implementation
Frankston City Council is delivering the Monterey Reserve Master Plan through a staged program of improvements that will transform Monterey Reserve into a more accessible, inclusive and vibrant community destination for people of all ages and abilities. The project will deliver new recreation opportunities, improved park amenities, increased tree planting and upgraded community infrastructure over a number of stages.
Stage 1: Youth Space
The Youth Space has been designed to create a safe, active and engaging destination for young people while improving the overall amenity of Monterey Reserve. Construction of Stage 1 is expected to commence in early 2027 and will deliver the new youth-focused recreation precinct featuring:
- Skate park
- Multi-use court
- Parkour zone
- New pathways and connections
- Seating, bike parking and park furniture
- Tree planting and landscaping
- Improved accessibility and drainage infrastructure
Future Stages
Council is also progressing the design development work for future stages for Monterey Reserve as per the adopted Master Plan to guide future investment and funding opportunities. Planned improvements being investigated include:
- A new district-level playground
- Accessible and inclusive play opportunities
- Multigenerational recreation spaces
- Walking and jogging circuit paths
- Additional tree planting and landscape improvements
- Upgraded picnic areas, shelters and barbecues
- Kickabout and informal recreation spaces
- Reserve-wide lighting upgrades
- Improved accessible public toilets
- A Changing Places facility
- Improved paths and accessibility connections throughout the reserve
Future works will be delivered progressively as funding becomes available. Details of the design development will be shared with community to demonstrate how they align with the adopted Master Plan and prior community consultation.
Project Timeline
Stage 1 Youth Space
- Construction commencement: January 2027
- Construction completion: April/May 2027
Future Stages
- Design development: 2026-2027
- Construction delivery: Subject to future funding and Council approval
Anticipated Delivery Timelines
|
Works Package
|
Construction (FY)
|
|
Play and multigenerational spaces
|
2027 -2028
|
|
Circuit path, lighting and tree planting
|
2028 -2029
|
|
Picnic area and kickabout space
|
2028 -2029
|
|
Carpark upgrade
|
2028 -2029
|
|
Public Toilet
|
2028 -2029
|
All dates are indicative and subject to change.
During Construction
During construction, parts of the reserve will be temporarily fenced for safety to accommodate the construction of Stage 1: Youth Space. Wherever possible, the remainder of the reserve will remain open and accessible to the community. Measures will be implemented to minimise impacts on residents, visitors and the surrounding environment.
Stay Updated
This page will be updated as the project progresses, including key milestones, design updates and opportunities for community engagement.
For more information, contact Frankston City Council on 1300 322 322.